ACTION 6.2.3

Increase code Enforcement efforts with a clear pathway to permitting with the adoption of OpenGov software. Develop the software tools to integrate interoperable Code review and approval between applicable Departments.

In Progress
Current Status
OpenGov software implementation is rolling out enterprise wide. Electrical permits are live, with residential, plumbing, gas fitter and project permits nearing completion in the next weeks. The stack order will be to buildout Building then move onto Fire. Water, sewer, excavation and driveway permits go live date March 31, 2025

Key Performance Indicators

Lower the number of incomplete or late permit applications.
In Progress
Timeline: 2025
Due Date: N/A
Responsible: Public Works Planning and Development
KPI Details