ACTION 7.5.2

Develop and implement projects for identified existing gaps and areas where sidewalks are needed

In Progress

Key Performance Indicators

Construct the section of sidewalk on the Miracle Mile from Price Chopper to Poverty Ln. in 2023.
In Progress
Description


Current Status

The sidewalk has been built. Finishing touches will occur in Spring of 2024. Sidewalk on Old Etna Road to Rt 120 is contracted to be constructed in 2025. A multi-use path was constructed on Lahaye Drive between Mt Support and Route 120 in 2024.

Timeline: 2024, 2025
Due Date: N/A
Responsible: Public Works
Construct the section of sidewalk on Mechanic Street from the American Legion to Slayton Hill Rd. NLT the end of 2025.
In Progress
Description


Current Status

Preliminary design is in process. Construction is scheduled for spring/summer of 2025. Due to cost overruns funding from the general fund was necessary to complete the project which is presently out to bid.

Timeline: 2024, 2025
Due Date: N/A
Responsible: Public Works
Construct the section of sidewalk from Etna Road to Mount Support
Planned
Description


Current Status


Timeline: 2026
Due Date: N/A
Responsible: Public Works Planning and Development