ACTION 7.7.2

Create a project schedule for all DOT related Projects

In Progress

Key Performance Indicators

Submit for 10 year plan and CIP in identified problem areas
In Progress
Current Status
2025 – Trues Brook Road bridge is scheduled to start in 2025 completion in 2026. High Street intersection is scheduled to start in summer of 2025 and be completed in 2026. The Mechanic Street sidewalk from Slayton Hill to the American Legion scheduled for construction in the summer of 2025. Hanover Street Bridge is scheduled for 2026. Lahaye Drive/Mount Support intersection final pave is scheduled for 2025
Timeline: 2025
Due Date: N/A
Responsible: Public Works