Transportation
7.3
7.3 Airport: Support efforts to maintain general aviation.
Strategic Objective
4
Total Actions
0
Planned
4
In Progress
0
Completed
0
Stalled
Actions
Strategic actions under this objective
All Years
2024
2025
2026
2027
2028
2029
2030
7.3.1 Development of Plans to support infrastructure for electric powered aircraft.
Key Performance Indicators
Determine power grid requirements for charging aircraft in design and testing phases.
Implement alternative energy generation at airport.
Install transformers needed to charge electric aircraft.
Estimated aircraft certification date is 2028.
Airport
In Progress
View Details
7.3.2 Rehabilitate general aviation aprons
Key Performance Indicators
Rehabilitate South and Echo aprons
Rehabilitate of aprons programmed into NH DOT CIP for FY 2026–2027. Program may slip one or two years depending.
Airport
In Progress
View Details
7.3.3 Enhance General Aviation (GA) storage capacity based on need
Key Performance Indicators
Bipartisan Infrastructure Law (BIL) funding to construct additional 10 bay T-hangar
Install electric chargers based on need.
Cape Air electric aircraft scheduled for service
Airport
In Progress
View Details
7.3.4 Market general aviation services
Key Performance Indicators
Market airport's general aviation service
Airport
In Progress
View Details