ACTION 7.4.2

Develop a trail maintenance plan in order to ensure that TCI of MRG and NRT is maintained to the standard

In Progress

Key Performance Indicators

Finalize negotiations with NHDOT to discontinue the section of RR property from Glen Rd. to Riverside Park in 2023. Initiate proceedings with the Federal Surface Transportation Board to discontinue this section of RR in 2023. Complete process with the STB by July of 2024. Execute an agreement with NH DOT to add this section to the rail trail agreement adding this section to the MRG NLT December 2024.
In Progress
Current Status
NH DOT is still stalling on approving the Surface Transportation Board (STB) Abandonment filing. No design work begins until STB approval. Powerhouse Mall alignment design work began Winter 2025.
Timeline: 2025
Due Date: N/A
Responsible: Public Works Recreation, Arts, and Parks